This week was a major consolidation week, bringing the South and West walls all the way up to the 24th course (16′ above slab level).  The East wall, which used to be our tallest wall, lags two courses below that, and our North Wall lags another two courses lower still.  Here was our condition at the start of the week, with the West wall growing up from the 16th course:

fisheyecourse16.jpg

And another perspective, from ground level.  Note the two masons on the right holding a tape measure between them.  Every block is measured in:

fisheyegroundlevel.jpg

And despite the painstaking work, by lunchtime, four courses are up on the South Wall, reaching the 24th course.  Amazing!

southwallcourse24outer2.jpg

Because we lay in ladder wire to span the cavity every two courses, and because the masons laid up four courses in one go, the masons needed to support the ladder wire until the inner wythe could contain it, hence the momentary appearance of vertical blocks:

southwallladderwire.jpg

Studio designer Wes Lachot makes a cameo appearance as the ladder wire is given a proper burial into the inner wythe:

southwallcourse22inner.jpg

Note above the use of our hand-cranked pallet lift.  From here on up, it’s just too much to “throw” the blocks up.  Speaking of “up” (which was a great movie by the way), we’ve just about reached the limit of our scaffolding this week, so a new batch was ordered—enough to get us up to 24′:

scaffolding.jpg

More evidence that blocks are going up:

blockshadows.jpg

Yesterday the West wall reached the 22nd course:

westwallcourse22outer.jpg

And today you can see that the outer wythe has reached the 24th course, behind the 23-course-high inner wythe:

westwallcourse23inner.jpg

Look closely and you’ll see that the upper diffusion pattern is starting on that 23rd course:

westwallupperdiffusion.jpg

And here you can see a nice little touch…an “echo” of the diffusion pattern expressed on the outer wythe:

displacedblocks.jpg

We’re really digging into the blocks now:

rpgcourse24.jpg

Even the mortar sand pile is getting smaller:

mortarsandcourse18-half.jpg mortarsandcourse24-half.jpg

Yow!  That’s enough of a report for me.  But stay tuned for some very exciting new developements…I promise!

Author: Michael Tiemann

Open source pioneer. Red Hat Executive. UNCSA Trustee. Ninja.

One thought on “Week 75 (The 24th Course)”

  1. Looking really good! Your mason’s helpers need to be fired though, the site is a mess! /giggle I’ll drive down there next week and clean it up for you. Nothing worse than a messy construction site. /giggle Seriously though, things look like they’re coming along quite nicely!

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: