We got a large truckload of gravel delivered this week, seen here in two large piles:
Not very exciting, I know, but it is progress. There has also been a lot more progress on the mechanical conduit layer, with manifold inputs taking their place in the blocks in Booth A:
And one of the bathrooms:
And I found out what the green spraypaint on the blocks means…
It means “to be knocked out for more manifold feeders”, as seen in these views of the Utility Room:
And the Audio eQuipment Room:
Later in the week one of the large gravel piles was moved and tamped into most of the studio slab area:
And looking in the other direction:
Finally, some shots of what will become the slab for the Loggia:
We found a few errors and omissions in our final pre-slab-pouring walkthrough that will be corrected next week. If we are lucky, the slab will be poured before American Thanksgiving. Won’t that be something to be thankful for?