Construction photos: week 10

My apologies that there was no week 9. There was no visible progress as most of the work was finalizing the order for the blocks. The order is in, and we expect deliveries in about 4 weeks and the last blocks to be delivered by the end of April. Yipee!

This week we finished the wiring plan, down to the point of actually placing nails and string where pipe conduit is to go. The updated wiring plan looks something like this:

wireplan-24×36.pngFull 24×36 3/16 scale plan

And here’s what it all looks like in real life:

The wiring overview
Control Room wiring trough
Paths flowing into audio eQuipment Room (QR)
Pipe locations inside QR and video Machine Room (MR)

The string doesn’t show up well in the thumbnails, but it’s there. For some more details, here are views of the networks that will live under the Music Room and Booth floors. Note how all the pathways travel “through” doors.

Music Room and Booth networks Music Room detail

Finally, the view of everything coming into “Grand Central”. This is the space below the Control Room window. 11 analog audio and 7 digital/video pipes make for a very full space down there!

View from Grand Central

Next up: laying the pipe and pouring the slab!

Author: Michael Tiemann

Open source pioneer. Red Hat Executive. UNCSA Trustee. Ninja.

One thought on “Construction photos: week 10”

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: