Manifold Recording / The Miraverse

October 31, 2010

Week 147 (Music Room Floor, Part 2)

Filed under: construction photos — Michael Tiemann @ 9:51 pm

Started in earnest last week, the floor of the Music Room remains this week’s major production.  And indeed, progress is looking good:

Here is that progress from another perspective:

(more…)

October 23, 2010

Week 146 (Music Room Floor, Part 1)

Filed under: construction photos — Tags: — Michael Tiemann @ 2:37 pm

The installation of the wood floor in the Music Room is now in full swing, for real this time.  Here are three perspectives of first twelve diamonds:

Despite the awful spectrum of the mercury-vapor work lamp, these images do show how the wood appears to change color as one moves around the room.  It should be even more dramatic once the wood is finished.

So, what makes this such a challenge to install?  Read on…

(more…)

October 16, 2010

Week 145 (IAC Door Installation)

Filed under: construction photos — Michael Tiemann @ 5:09 pm

This week our door installation team hung 12 more IAC  doors, all in the Main building.  In this photo you can see 9 of them (if you know what to look for):

That’s one and a half tons of hardware that moves with effortless precision.  Let’s rewind a bit to see how we got here (and to see what else was accomplished)…

(more…)

October 9, 2010

Week 144 (IAC Doors Arrive)

Filed under: construction photos — Michael Tiemann @ 8:54 pm

We are still hoping to “open our doors” by the end of the year, and to do so we really need two things to happen:

  1. The delivery of doors
  2. A timely commissioning of our two consoles

Early Monday morning, and right on schedule, a truck pulled up to the site carrying 12,000 pounds of hardware and packaging from the Industrial Acoustics Company.  This directly addresses item #1, but it also critically enables item #2, because we have a lot of work to do before we are even ready to begin the console commissioning process.  Nevertheless, we do have a schedule that works if everybody delivers according to plan, and IAC did their part to initiate our 6-week sprint with an excellent start:

(more…)

October 3, 2010

Week 143 (Rope Lights)

Filed under: construction photos — Michael Tiemann @ 11:03 pm

This week was mostly progress on smaller things, which is sometimes needed so that bigger things can get done.  With our spiffy new cloud in the Music Room, we put up the finishing touch of some LED rope lights:

That’s just after they were installed by the electrician, but just before they were finally hidden with trim:

(more…)

Theme: Customized WordPress Classic. Blog at WordPress.com.

Follow

Get every new post delivered to your Inbox.